Concrete Footing Calculator

Concrete for strip and pad footings — and, before that, what width the code actually requires for your soil and storeys.

What each dimension means

RunDW
FootingTotal run in feet; width and depth of the trench in inches.

How to use this calculator

  1. Not sure what size to build? Start in sizing mode with your soil bearing and storey count.
  2. For a perimeter footing, enter the total run measured along the centre of the trench.
  3. For pads, enter one pad and the number of them — the calculator gives the per-pad bag count too.
  4. Check which figure governed the width: the code table, or the 2 in projection rule.

How the calculation works

A footing does one job: spread the weight of the building over enough soil that the soil can carry it. That makes its width a structural decision, not a preference — and it is the question people actually arrive with. So this calculator has three modes: work out the concrete for a footing you have already sized, work out pad footings for point loads, or work out what size the footing needs to be in the first place.

The sizing mode uses IRC Table R403.1(1), the table your building department is most likely to be reading from. Width comes from the soil bearing capacity and the number of storeys above; thickness is a minimum of 6 inches and must be at least as much as the footing projects past the wall. Both are minimums, and both are superseded by a stamped plan.

  • Continuous footingV = run × width × thickness ÷ 27
  • Pad footingsV = width × length × thickness × count ÷ 27
  • Minimum widthmax(IRC table, wall thickness + 4 in)
  • Minimum thicknessmax(6 in, projection each side)
  • Rebar piecesceil(run ÷ 18 ft) × bars

Soil bearing is the number everything else hangs off

The IRC assumes 1,500 psf unless you can show better, and that default is why 16 inch footings are so common in residential work. Prove 2,000 psf and the same one-storey footing drops to 12 inches — a quarter less concrete around the whole perimeter. Prove 3,000 and it drops to 8. This is the single biggest lever on footing cost, and on a large build a soils report can pay for itself several times over. Guessing upward, on the other hand, is how buildings settle.

Why the calculator sometimes ignores the table

At higher bearing values the table gives widths narrower than the wall standing on them — 6 inches under an 8 inch wall. The projection rule then takes over: a footing must project at least 2 inches past each face, so the practical minimum becomes the wall thickness plus 4 inches. The result line tells you which of the two governed, because that tells you whether a better soils number would actually buy you anything.

Projection and thickness are linked

A footing works by cantilevering out from under the wall, and an unreinforced concrete cantilever can only reach about as far as it is deep before it wants to crack off. That is the rule behind "projection shall not exceed thickness". A 24 inch footing under an 8 inch wall projects 8 inches each side, so it needs to be at least 8 inches thick — not the 6 inch minimum. Wide and thin is the classic error.

Continuous footings and pad footings do different jobs

A continuous or strip footing runs under a wall and spreads a line load. A pad footing sits under a single point — a post, a column, the end of a beam — and spreads a concentrated one. Most houses have both, and the pads are the ones people forget until the deck posts have nowhere to land. A post can also be set straight into a dug hole rather than landing on a pad — post-hole-concrete-calculator covers that case, and it is the cheaper one where the load is light. Pads have to be centred under their load; a pad off to one side rotates rather than bears. Once the footing is sized, concrete-wall-calculator takes it from there.

Rebar in footings, and the laps that make it work

The IRC does not require reinforcement in every residential footing, but two continuous bars is near-universal practice and cheap insurance against differential settlement. The calculator sizes the bar count from the width, allowing 3 inches of cover to earth, and counts 20 ft stock lengths with 2 ft laps. Bars butted end to end transfer nothing at all — the lap is the entire mechanism, and corners want bent bars or an L-shaped splice, not two bars meeting at a point. For mats and slab grids, rebar calculator.

Depth is a separate question from size

Nothing in the width calculation says how deep to dig. The bottom of a footing goes below the local frost line — which is 12 inches in parts of the south and over 6 feet in northern Minnesota — and never less than 12 inches into undisturbed ground. A perfectly sized footing above the frost line will still be lifted every winter.

Worked examples

Perimeter footing for a 40 × 24 ft house

Single storey, 1,500 psf soil, 8 in foundation wall, 16 in × 8 in footing.

Perimeter
2 × (40 + 24) = 128 ft
Section
16 in × 8 in = 1.33 × 0.67 ft
Volume
128 × 0.89 = 113.8 ft³
In yards
113.8 ÷ 27 = 4.21 yd³
Plus 10%
4.64 yd³

4.64 yd³ — order 5

Two continuous #4 bars, 128 ft each, is 16 stock lengths of 20 ft once 2 ft laps are allowed for. Trenches are never as neat as the drawing, which is what the 10% covers.

Sizing that same footing from scratch

One storey, 1,500 psf, 8 in wall — what does the code actually require?

Table R403.1(1)
1 storey at 1,500 psf → 16 in
Projection minimum
8 + 2 + 2 = 12 in
Width governs
max(16, 12) = 16 in
Projection each side
(16 − 8) ÷ 2 = 4 in
Thickness
max(6, 4) = 6 in

16 in wide × 6 in thick minimum

Most builders pour 8 inches thick anyway. The extra 2 inches over 128 ft is about a cubic yard — cheap next to the cost of being wrong, and it gives the bars proper cover.

Six pad footings for deck posts

24 in square, 12 in thick, one under each post.

Volume per pad
2 × 2 × 1 = 4 ft³
Six pads
24 ft³ = 0.89 yd³
Plus 10%
0.98 yd³
As 80 lb bags
44 bags total, 7 per pad

0.98 yd³ — bag it

Just under a yard, so bags win. Mix each pad in one go rather than topping up a part-set pad later.

Reference tables

IRC minimum footing width, light-frame construction

Table R403.1(1). Minimums only — a stamped plan or your building department overrides these.

Soil bearing1 storey2 storeys3 storeys
1,500 psf16 in21 in32 in
2,000 psf12 in15 in23 in
3,000 psf8 in10 in15 in
4,000 psf6 in8 in12 in

Concrete per 100 linear feet of footing

WidthThicknessVolumeAs 80 lb bags
12 in6 in1.85 yd³84
16 in8 in3.29 yd³149
20 in8 in4.12 yd³186
24 in10 in6.17 yd³278
32 in12 in9.88 yd³445

What it costs

Footing concrete is $140–$200 per cubic yard delivered in 2026, with short-load fees of $50–$150 under about 4 yards. Excavation, forming, steel and placement typically bring an installed footing to $5–$12 per linear foot for standard residential work — meaning the concrete itself is usually the smaller half of the bill.

The lines that actually move the number

Excavation and spoil removal, forming where the trench will not stand, rebar, and access for the truck. A site the truck can chute into directly is the cheap case; anything needing a pump adds $800–$1,500 regardless of how little concrete is involved. Over-excavating a soft trench and filling the extra depth with concrete is a real and frequently unbudgeted cost.

Where the money is saved

Not by pouring thinner — by digging accurately and by knowing your soil. A neat trench of the right width can cut the pour by 10–15% against a ragged one, and a bearing capacity of 2,000 psf instead of the assumed 1,500 takes a one-storey footing from 16 inches to 12. On a 128 ft perimeter that is over a cubic yard saved before anything else changes.

Bags or a truck

Under about a cubic yard, bags are cheaper all-in and there is no delivery to schedule. Above that the arithmetic turns fast: 4.6 yards is 208 bags, over eight tons to move and mix, and a footing mixed in batches over a day has cold joints running through it. A short-load fee is almost always the better purchase.

Common mistakes

Making the footing wide but leaving it thin

Projection cannot exceed thickness. A 24 inch footing under an 8 inch wall projects 8 inches each side and needs 8 inches of depth, not the 6 inch minimum. Wide and thin cracks along the wall line and stops spreading load at all.

Assuming a soil bearing capacity you have not established

The code default of 1,500 psf exists for a reason. Sizing off 3,000 because the ground "looks solid" halves the footing width on an assumption nobody has tested — and settlement shows up years later, in the walls.

Sizing correctly and digging too shallow

Width answers how much soil carries the load. Depth answers whether the soil under it freezes. Below the local frost line and at least 12 inches into undisturbed ground, whatever the width calculation says.

Pouring onto disturbed or frozen ground

Backfill compacted by boots is not undisturbed soil, and it consolidates under load. Dig to firm bearing, and if you overdig, fill with compacted compacted base stone or with concrete — never with loose spoil.

Butting rebar instead of lapping it

Two bars meeting end to end transfer no tension whatsoever. Laps of about 40 bar diameters — 20 inches for a #4 — are what make a continuous run continuous, and corners need bent bars rather than two straight ones meeting.

Forgetting the pads

Perimeter footings get planned; the interior pads under posts, columns and beam ends get discovered on the day. They are part of the same pour and belong in the same order.

Frequently asked questions

How wide should a concrete footing be?

For light-frame construction on 1,500 psf soil, IRC Table R403.1(1) requires 16 inches for one storey, 21 for two and 32 for three. Better soil allows less — 12 inches for one storey at 2,000 psf. The footing must also project at least 2 inches past each face of the wall, so the practical minimum is never less than the wall thickness plus 4 inches.

How thick should a footing be?

At least 6 inches, and never less than the distance it projects past the wall. A 24 inch footing under an 8 inch wall projects 8 inches each side and therefore needs to be 8 inches thick. Wide and thin is the classic failure — the projection cracks off and stops spreading load.

How much concrete do I need for a footing?

Run × width × thickness, all in feet, divided by 27. A 128 ft perimeter at 16 by 8 inches is 4.21 cubic yards before waste, so order about 4.6. A hundred linear feet of 16 by 8 inch footing takes 3.29 cubic yards.

How deep do footings need to be?

Below the local frost line, and at least 12 inches into undisturbed ground. Frost depth ranges from about 12 inches on the Gulf coast to over 6 feet in northern Minnesota — your building department publishes the figure. Depth is a completely separate question from width, and a correctly sized footing above the frost line still heaves.

Do footings need rebar?

The IRC does not require it in every residential footing, but two continuous bars is near-universal practice and cheap insurance against differential settlement. Lap the bars about 40 bar diameters — 20 inches for a #4 — because bars butted end to end transfer no load at all.

What is the difference between a strip footing and a pad footing?

A strip or continuous footing runs under a wall and spreads a line load. A pad footing sits under a single point — a post, a column, a beam end — and spreads a concentrated one. Most houses need both, and the interior pads are the ones most often forgotten until the day of the pour.

Can I pour footings without forms?

Yes, where the trench holds its own shape in firm undisturbed soil — that is the normal and cheapest case. Forms are needed in loose or sandy ground, or where the footing stands proud. Never pour against loose backfill: it consolidates under load and the footing settles with it.

Related calculators

Put this calculator on your site

Embed the Concrete Footing Calculator anywhere — it is free, stays in sync with this page, and sizes itself to fit. The only condition is the credit line in the snippet, which links your readers to the full version with the formulas and worked examples.

<!-- Concrete Footing Calculator — free embed from BuildCalculators.com -->
<div data-buildcalculators="concrete-footing-calculator"></div>
<script async src="https://buildcalculators.com/embed.js"></script>
<p>Free concrete footing calculator by <a href="https://buildcalculators.com/concrete-footing-calculator">BuildCalculators</a></p>

How this number was worked out

This calculator uses published constants from named industry sources, each asserted in an automated test that runs on every build. The formula is printed with the result above, and any correction we make is logged on the changelog.

It is a planning estimate. It does not replace an engineer, a site visit or a written quote — confirm quantities with your supplier before ordering.