Concrete Wall Calculator

Concrete, rebar and formwork for a poured wall — single walls or a full perimeter measured on the centreline.

What each dimension means

RunDW
FootingTotal run in feet; width and depth of the trench in inches.

How to use this calculator

  1. For a whole foundation, use perimeter mode and enter the building dimensions — it runs the centreline for you.
  2. Deduct window and door areas, but budget the extra formwork they create.
  3. Enter the bar spacing from your plan; this counts steel, it does not specify it.
  4. Read the form face area — that is the number a forming contractor prices from.

How the calculation works

A poured wall is the easiest volume on this site — length by height by thickness — and the hardest thing to actually order, because the concrete is only one of four quantities that come off the same wall and they all scale differently. Double the thickness and the concrete doubles while the formwork does not move. Deduct a window and the concrete drops while the formwork goes up.

So this calculator gives you all four: the concrete, the vertical steel, the horizontal steel, and the form face area that the forming will actually be priced against. The perimeter mode works the run out from building dimensions on the centreline, which is what stops the four corners being counted twice.

  • Wall volumeV = (run × height − openings) × thickness ÷ 27
  • Centreline perimeter2(L − t) + 2(W − t)
  • Vertical barsfloor(run × 12 ÷ spacing) + 1
  • Horizontal barsfloor(height × 12 ÷ spacing) + 1
  • Form face areanet wall face × 2

Centreline, or you pay for the corners twice

Take a 40 by 24 ft building with 8 inch walls. Using the outside dimensions gives a 128 ft perimeter; the real centreline run is 2(40 − 0.67) + 2(24 − 0.67), or 125.3 ft. The 2.7 ft difference is the four corners, where two walls overlap and the concrete is only there once. On an 8 ft high wall that is a third of a cubic yard you would otherwise order and pay for twice.

Bar counts are gaps plus one

Spacing measures the distance between bars, so the number of bars is always one more than the number of gaps. A 40 ft wall with vertical bars at 48 inches has ten gaps and eleven bars. This is the same arithmetic that catches people on slab grids, and it is off by one in the direction that leaves you short.

This is a takeoff, not a specification

The spacings you enter here get counted, not checked. What your wall actually needs comes from IRC Table R404.1.2 or from an engineer, and it depends on the wall height, its thickness, the soil class and — most of all — how much unbalanced backfill pushes against it. A basement wall retaining 7 ft of soil is a different structure from a 4 ft garden wall of the same thickness, and no rule of thumb bridges that gap safely.

Cover is what makes the steel last

Three inches of concrete where it is cast directly against earth, an inch and a half on formed faces that will be exposed to earth. Bars pushed tight against a form have no protection: water reaches them, they rust, rust occupies more volume than steel, and the face of the wall spalls off in sheets a decade later. Chairs and spacers are cheap.

Openings subtract concrete and add work

A window buck removes its own area of concrete and then adds two faces of formwork, bracing to stop it floating up in the pour, and a lintel or bond beam over the top. The form area in the results covers the wall faces only. On a wall with several openings, the forming labour can rise while the concrete bill falls — which is exactly backwards from how most people budget it.

A wall is a continuous pour

Formed walls go in in lifts and get vibrated as they rise. That is not a bagged job at any realistic size: a 40 ft wall 8 ft high in 8 inch thickness is nearly 8 cubic yards, or 356 bags. Placing it in batches over a day leaves a cold joint running horizontally through the wall at whatever height you stopped — a plane of weakness, and on a basement wall, a place for water to come through.

Worked examples

A single 40 × 8 ft wall, 8 in thick

No openings, bars at 48 in vertical and 24 in horizontal.

Face area
40 × 8 = 320 ft²
Volume
320 × 0.667 = 213.3 ft³
In yards
7.90 yd³
Vertical bars
480 ÷ 48 = 10 gaps → 11 bars
Horizontal bars
96 ÷ 24 = 4 gaps → 5 runs

8.30 yd³ with waste, 288 lin ft of rebar

Also 640 ft² of form face, both sides. That number, not the concrete, is what a forming subcontractor prices from.

A full 40 × 24 ft foundation perimeter

8 ft high, 8 in thick, 32 ft² of openings deducted.

Centreline run
2(40 − 0.67) + 2(24 − 0.67) = 125.33 ft
Gross face
125.33 × 8 = 1,002.7 ft²
Less openings
970.7 ft²
Volume
970.7 × 0.667 = 647.1 ft³ = 23.97 yd³

25.17 yd³ with waste

Using the 128 ft outside perimeter instead would have added 0.53 yd³ — about $90 of concrete bought to fill corners that are already full.

A 30 × 4 ft garden wall, 6 in thick

Low freestanding wall, bars at 32 in vertical.

Face area
30 × 4 = 120 ft²
Volume
120 × 0.5 = 60 ft³
In yards
2.22 yd³
Vertical bars
360 ÷ 32 = 11 gaps → 12 bars

2.33 yd³ with waste

Still a truck, and still worth one — 2.33 yards is 105 bags. A freestanding wall this low usually needs far less steel than a retaining one, but it needs a footing just the same.

Reference tables

Concrete per 100 ft² of wall face

ThicknessVolumeCubic yards80 lb bags
6 in50.0 ft³1.85 yd³84
8 in66.7 ft³2.47 yd³112
10 in83.3 ft³3.09 yd³139
12 in100.0 ft³3.70 yd³167

Concrete cover over reinforcement

ACI 318 minimums for cast-in-place concrete.

ConditionMinimum cover
Cast against and permanently exposed to earth3 in
Formed, then exposed to earth or weather (#6 and larger)2 in
Formed, then exposed to earth or weather (#5 and smaller)1½ in
Not exposed to weather or earth¾ in

What it costs

Poured foundation walls run $25–$60 per square foot of wall face installed in 2026, taking in forming, steel, concrete, placement and stripping. The concrete itself is $140–$200 per cubic yard, which on a typical 8 inch wall is only about $4 per square foot of face — well under a fifth of the installed price.

Forming is most of the bill

Forms have to be set plumb, tied against several tons of lateral pressure, and stripped clean. Renting forms runs $1.50–$4 per square foot of face per use; buying and building them costs more up front and pays off only across several jobs. This is why the form face area is a headline result here rather than a footnote.

Thickness is cheaper than height

Going from 8 to 10 inches adds 25% to the concrete and almost nothing to the forming, since the forms are the same panels set further apart. Going from 8 to 10 feet high adds 25% to both, plus taller bracing and a slower pour. Where a wall needs more capacity, thickness is usually the cheaper way to buy it — but that is a structural decision, not a budget one.

Pump access

A truck that can chute straight into the forms is the cheap case. Anything else means a pump at $800–$1,500 for the day regardless of volume, and on a tight or sloping site that is effectively a fixed cost of pouring at all. Worth establishing before the forms go up, not after.

Common mistakes

Using outside dimensions for a perimeter

The four corners get counted twice. Run the perimeter on the centreline — outside dimensions less one wall thickness per side — or you buy concrete to fill corners that are already full.

Counting gaps instead of bars

A 40 ft wall at 48 inch spacing has ten gaps and eleven bars. Dropping the plus-one leaves you one bar short in every direction, and it is always the end bar that goes missing.

Treating the spacing you typed as the spacing you need

This tool counts what you tell it. Wall reinforcement depends on height, thickness, soil class and unbalanced backfill, and comes from IRC Table R404.1.2 or an engineer. A garden wall and a basement wall of the same size are not the same structure.

Ignoring cover

Steel needs 3 inches against earth and 1½ inches on formed faces exposed to earth. Bars tied against the form rust, and rusting steel spalls the face off the wall.

Budgeting openings as a saving

A window removes concrete and adds formwork, bracing and a lintel. On a wall with several openings the labour goes up while the concrete goes down.

Pouring a wall in batches

A wall is placed in continuous lifts and vibrated. Stopping for hours leaves a cold joint across the whole wall — a weakness, and on a basement wall a route for water.

Frequently asked questions

How much concrete do I need for a wall?

Length × height × thickness, divided by 27, minus any openings. A 40 by 8 ft wall at 8 inches thick is 213 cubic feet, or 7.9 cubic yards. Per 100 square feet of wall face, an 8 inch wall takes 2.47 cubic yards.

How do I calculate concrete for a foundation perimeter?

Run the perimeter on the CENTRELINE, not the outside face — outside dimensions less one wall thickness per side. A 40 by 24 ft building with 8 inch walls has a 125.33 ft centreline, not 128 ft. The 2.67 ft difference is the four corners, where two walls overlap and the concrete is only there once.

How much rebar does a concrete wall need?

That depends on the wall height, thickness, soil class and how much unbalanced backfill pushes against it, and it comes from IRC Table R404.1.2 or an engineer. This calculator counts the steel for a spacing you supply — a 40 ft wall with vertical bars at 48 inches takes 11 bars, because spacing counts the gaps and there is always one more bar than gaps.

How much concrete cover does wall rebar need?

Three inches where concrete is cast directly against earth, and 1½ inches on formed faces later exposed to earth or weather for #5 bars and smaller. Bars tied against the form rust, and rusting steel expands and spalls the face off the wall.

What does a poured concrete wall cost?

$25–$60 per square foot of wall face installed in 2026, covering forming, steel, concrete, placement and stripping. The concrete alone is about $4 per square foot on an 8 inch wall — under a fifth of the total, because forming is most of the work.

Can I pour a concrete wall in sections?

Not in horizontal sections. A wall goes in in continuous lifts and gets vibrated as it rises; stopping for hours leaves a cold joint running through the whole wall — a plane of weakness, and on a basement wall a route for water. Vertical construction joints at planned locations are a different thing and are fine.

Is a poured wall better than block?

For a foundation, poured is usually faster and monolithic, and often cheaper once forming is priced in. Block wins where access is tight — no truck or pump, material carried in by hand — and where the work has to happen in stages by one person.

Related calculators

Put this calculator on your site

Embed the Concrete Wall Calculator anywhere — it is free, stays in sync with this page, and sizes itself to fit. The only condition is the credit line in the snippet, which links your readers to the full version with the formulas and worked examples.

<!-- Concrete Wall Calculator — free embed from BuildCalculators.com -->
<div data-buildcalculators="concrete-wall-calculator"></div>
<script async src="https://buildcalculators.com/embed.js"></script>
<p>Free concrete wall calculator by <a href="https://buildcalculators.com/concrete-wall-calculator">BuildCalculators</a></p>

How this number was worked out

This calculator uses published constants from named industry sources, each asserted in an automated test that runs on every build. The formula is printed with the result above, and any correction we make is logged on the changelog.

It is a planning estimate. It does not replace an engineer, a site visit or a written quote — confirm quantities with your supplier before ordering.