Priced as unreinforced. Check before you accept a quote on that basis — mesh in an old slab is invisible until it is broken, and finding it is a legitimate reason for a contractor to come back for more money.
Published averages for concrete removal run $3–$8 per square foot, but that figure blends thin patios with thick reinforced driveways. This tool starts from the plain 4 in case and adds for what is actually there, which is why a simple patio comes out below the headline number and a reinforced driveway above it.
Access decides the rest. A machine that can reach the slab is fast; anything hand-broken and barrowed out through a gate is a different job at a different price. 10.0 tons is roughly 1 skip loads or one small dumpster per 8 to 10 tons.
Calculated with BuildCalculators.com
Calculated with BuildCalculators.com · buildcalculators.com/concrete-removal-cost-calculator
Estimates are for planning only — confirm quantities with your supplier or contractor before ordering.
How to use this calculator
Check a cut edge or joint for mesh before you assume the slab is unreinforced.
Enter the real thickness — a driveway is usually 5 or 6 in, not 4.
Read the debris weight; it decides the truck, the dumpster and the number of trips.
Switch to DIY mode to see the disposal cost on its own, before equipment and your time.
How the calculation works
Tear-out is the line that turns a replacement into a bigger job than anyone budgeted for, and it is the line most often missing from a quote. On a 480 square foot driveway it is routinely a fifth to a quarter of the whole project — and unlike the new pour, there is nothing to show for it afterwards.
Two things drive the price: how much concrete there is, and whether there is steel in it. Thickness matters less than people expect, because roughly half a removal bill tracks the area — saw cutting, edge work, moving around the site — and only half tracks the volume that actually has to be broken and carried. Reinforcement matters more than people expect, because the mesh holds the fragments together and has to be cut out as the slab comes up.
The calculator also gives you the debris weight, which is the number that decides everything about disposal. A 4 inch slab weighs 50 pounds a square foot. A modest patio is several tons.
Why the published average does not match a simple patio
Search for concrete removal and you will find $3 to $8 per square foot. That average blends thin unreinforced patios with thick reinforced driveways, so it is high for one and low for the other. This tool starts from the plain 4 inch unreinforced case at $2 to $6 — the figure quoted throughout the rest of this site — and adds for thickness and steel separately. A 6 inch reinforced driveway lands at $3.50 to $10.50, which is where it should.
The weight is what makes this different from other demolition
Concrete is 150 pounds per cubic foot, so a 4 inch slab is 50 pounds per square foot and a 6 inch one is 75. A 20 by 20 patio at 4 inches is 10 tons. That is not a skip; it is several. It is also why a pickup is limited by payload rather than bed volume — a half-ton truck takes half a ton, which is about ten square feet of 4 inch slab per trip, and an overloaded pickup carrying concrete is genuinely dangerous to stop.
Reinforced or not, and how to tell before you commit
Look at a cut edge, an expansion joint or a corner that has spalled. Exposed wire or bar is obvious; a saw cut through the slab shows the section. Age is a weak signal — mesh has been common in residential work since the 1950s, and its absence in a driveway is more surprising than its presence. This matters because a contractor who priced unreinforced and then finds mesh has a legitimate claim for more money, and finding out on the day is the worst time.
Clean concrete is a resource, not waste
Recyclers crush old concrete into base stone and sell it, which is why clean concrete has a lower gate fee than mixed rubble and is occasionally taken free. The word doing the work is clean: rebar, wire, dirt, roots or timber in the load move it to the expensive rate, and some yards reject it outright. Sorting the steel out as you break is unpleasant and it pays.
Breaking it yourself, honestly
A 4 inch unreinforced patio is a realistic weekend with a rented electric breaker and a sledge. A 6 inch reinforced driveway is not — it wants a machine, and hiring the job is usually cheaper than renting the equipment and losing the weekend. The DIY figures here are disposal only, deliberately: the equipment, the truck and your time are the real cost, and pretending otherwise makes the comparison useless.
What removal does not include
Getting the ground ready for what comes next. Once the slab is out you have a hole with a compacted, often contaminated subgrade that has been under concrete for decades. Regrading, new base stone and compaction are part of the new pour, not part of the removal — and they are the other half of why replacement costs so much more than a first-time pour on open ground.
Worked examples
A 20 × 20 ft patio, 4 in, unreinforced
Hiring it out, decent machine access.
Area
400 ft²
Thickness factor
0.5 + 0.5 × 1 = 1.00
Rate
$2–$6 per ft²
Cost
$800–$2,400
Debris
4.94 yd³, 10 tons
$800–$2,400
Ten tons off a patio you could walk across in six paces. The weight is always the surprise.
A 12 × 40 ft driveway, 6 in, reinforced
The common replacement job.
Area
480 ft²
Thickness factor
0.5 + 0.5 × 1.5 = 1.25
Base rate
$2.50–$7.50
Plus reinforcement
$3.50–$10.50 per ft²
Cost
$1,680–$5,040
$1,680–$5,040, and 18 tons of debris
Against a new driveway at roughly $5,000–$9,000, the tear-out really is a quarter to a third of the project. A quote that does not name it separately is hiding it somewhere.
The same patio, broken and hauled yourself
400 ft², 4 in, 10 tons, a $120 per ton gate fee.
Weight
10 tons
Disposal
10 × $120 = $1,200
Half-ton pickup loads
20 trips
Equipment
Breaker hire, plus the weekend
$900–$1,500 in disposal alone
Twenty round trips to the recycler. At this size, hiring the removal at the low end of $800–$2,400 is competitive with doing it yourself once the truck and the breaker are priced.
Reference tables
What a slab weighs
Normal-weight concrete at 150 lb per cubic foot.
Thickness
Per ft²
100 ft²
400 ft²
4 in
50 lb
2.50 tons
10.00 tons
5 in
63 lb
3.13 tons
12.50 tons
6 in
75 lb
3.75 tons
15.00 tons
8 in
100 lb
5.00 tons
20.00 tons
Removal rate by what is in the slab
Per square foot, including disposal, with machine access.
Slab
Factor
Unreinforced
Reinforced
4 in
1.00
$2–$6
$3–$9
5 in
1.13
$2.25–$6.75
$3.25–$9.75
6 in
1.25
$2.50–$7.50
$3.50–$10.50
8 in
1.50
$3–$9
$4–$12
What it costs
Removal runs $2 to $12 per square foot depending on thickness, reinforcement and access, with disposal included. Doing it yourself, the gate fee alone is $90 to $160 a ton at a landfill and frequently less at a concrete recycler — sometimes nothing, if the load is clean.
Access is the whole variable
A slab a mini-excavator can reach comes up in hours. The same slab behind a house, through a 36 inch gate, hand-broken and barrowed, is a different job at several times the price. This is the single biggest reason two removal quotes on the same driveway differ, and it is worth walking the route with the contractor before either of you assumes anything.
Where DIY genuinely wins and where it does not
Under about 200 square feet of unreinforced 4 inch slab, breaking it yourself saves real money — a day with a rented breaker and a few trips to the recycler. Above that, or with steel in it, the equipment hire, the truck trips and the sheer physical toll close the gap fast. Twenty pickup loads is not a saving; it is a fortnight of evenings.
Ask for it as a separate line
On a replacement, insist that tear-out and disposal are itemised rather than folded into a per-square-foot price for the finished job. It is the only way to compare two quotes, and it exposes the bid that has quietly left it out — which is the classic source of a mid-job change order.
Common mistakes
Leaving tear-out out of a replacement budget
It is a fifth to a third of the project, and there is nothing to show for it when it is done. Every replacement quote should name it as its own line.
Assuming a slab is unreinforced
Mesh has been standard in residential work for decades and is invisible until the slab is broken. It adds $1 to $3 per square foot and it is a legitimate reason for a contractor to come back for more. Check a cut edge or a joint first.
Underestimating the weight
A 4 inch slab is 50 pounds per square foot. A small patio is ten tons. This governs the truck, the dumpster, the number of trips and whether the driveway you are parking on can take the load.
Overloading a pickup
A half-ton truck carries half a ton — about ten square feet of 4 inch slab. A bed full of concrete is several times the payload, and an overloaded truck does not stop, steer or brake the way you expect it to.
Mixing the debris
Clean concrete is cheap or free to dispose of because it gets crushed into base stone. Rebar, dirt, roots or timber in the load moves it to the expensive rate, and some recyclers turn it away entirely.
Treating the empty hole as ready to pour
The subgrade under an old slab is compacted, often contaminated and rarely at the right level. Regrading, new base and compaction belong to the new pour, and they are why replacement costs so much more than pouring on open ground.
Frequently asked questions
How much does concrete removal cost?
$2–$6 per square foot for a plain 4 inch unreinforced slab including disposal, rising to $3.50–$10.50 for a 6 inch reinforced driveway. Published averages of $3–$8 blend the two, which is why a simple patio comes out below that figure and a reinforced driveway above it.
How much does it cost to remove a concrete driveway?
A 12 by 40 ft driveway at 6 inches and reinforced runs roughly $1,680–$5,040, and produces about 18 tons of debris. Against a new driveway at $5,000–$9,000, tear-out really is a quarter to a third of a replacement project.
How much does a concrete slab weigh?
About 150 lb per cubic foot, so 50 lb per square foot at 4 inches and 75 lb at 6. A 20 by 20 ft patio at 4 inches is 10 tons. That weight is what decides the dumpster, the truck and the number of trips.
Does reinforcement make concrete removal more expensive?
Yes, by $1–$3 per square foot. The mesh or bar holds the fragments together so the slab will not break into liftable pieces on its own, the steel has to be cut as the work goes, and some recyclers charge more for reinforced debris.
How do I know if my slab is reinforced?
Look at a cut edge, an expansion joint, or a corner that has spalled — exposed wire or bar shows immediately. Mesh has been common in residential work since the 1950s, so its absence in a driveway is more surprising than its presence.
How much does it cost to dispose of concrete?
$90–$160 per ton at a landfill, and often less at a concrete recycler because they crush it into base stone. Hauling it yourself, expect $30–$65 per pickup load. Keep the load clean: rebar, dirt or timber mixed in moves it to the expensive rate.
Can I break up concrete myself?
A 4 inch unreinforced patio under about 200 square feet is a realistic weekend with a rented breaker. A 6 inch reinforced driveway is not — once equipment hire and twenty pickup trips are priced, hiring the removal is usually cheaper and always faster.
How many pickup loads is a concrete patio?
A half-ton pickup carries half a ton, which is about ten square feet of 4 inch slab. A 400 square foot patio is therefore around 20 trips. Weight is the limit, not the bed — a truck bed full of concrete is several times its payload.
Embed the Concrete Removal Cost Calculator anywhere — it is free, stays in sync with this page, and sizes itself to fit. The only condition is the credit line in the snippet, which links your readers to the full version with the formulas and worked examples.
This calculator uses published constants from named industry sources, each asserted in an automated test that runs on every build. The formula is printed with the result above, and any correction we make is logged on the changelog.
It is a planning estimate. It does not replace an engineer, a site visit or a written quote — confirm quantities with your supplier before ordering.
Written and reviewed by Arif Hossain, Diploma in Civil Engineering (4 years). Last reviewed October 8, 2026. More concrete tools.